AbstractWhen a firm's systems department has insufficient resources to carry out all requested development projects immediately, managers serving on the Data Processing Steering Committee need to decide which project should be completed first, second, third, etc. This can be done by ranking the projects in sequence of a 'priority criterion'. In the past net present value (NPV) was used for this purpose. However, in a small systems department, where projects are carried out in series, NPV is inappropriate. A more accurate measure of priority is a project's 'net worth' divided by its duration.